Uttarkashi/New Delhi:
The blades of the auger machine drilling via the rubble of the collapsed Silkyara tunnel had been on Saturday caught within the particles, forcing officers to think about switching to different choices that would drag on the rescue of 41 staff trapped inside for 13 days by a number of weeks extra.
Officers at the moment are shifting focus to 2 options – guide drilling via the remaining 10 or 12 metre stretch of the rubble or drilling down 86 metres from above.
Advising persistence, Nationwide Catastrophe Administration Authority (NDMA) member Lt Gen (retd) Syed Ata Hasnain mentioned in Delhi ”This operation may take a very long time.” On the catastrophe website, worldwide tunnelling advisor Arnold Dix repeated his promise of getting the employees out ”by Christmas”.
Guide drilling would contain particular person staff coming into the already bored 47-metre stretch of the rescue passage, drilling for a short interval within the confined area after which popping out to let another person take over.
This, in keeping with Uttarakhand Chief Minister Pushkar Singh Dhami, may start as quickly because the tools caught within the deliberate escape passage is introduced out.
Heavy tools, already dropped at the location, was being put in place Saturday for vertical drilling that officers had earlier mentioned may take weeks. The method, Mr Hasnain mentioned, would start within the ”subsequent 24 to 36 hours”.
He indicated that was the faster of the 2 important choices now being thought-about.
Drilling was at a standstill for nearly your entire day Friday, however the extent of the issue was recognized Saturday when worldwide professional Dix advised reporters that the auger machine is ”busted”.
”Augering is completed… the auger is damaged, destructed,” he advised reporters.
”The mountain has once more resisted the auger, so we’re rethinking our strategy. I’m assured that the 41 males are coming residence,” he mentioned, insisting that they remained secure.
When requested to spell out a timeline, he mentioned, ”I’ve at all times promised that they are going to be residence by Christmas.”
The 25-tonne drilling machine, out of fee for now, consists of an auger – an enormous corkscrew-like system with a cutter at its finish. This has up to now created a horizontal passage of 46.8 metres into the rubble out of a complete estimated size of 60 metres.
A metal chute had been pushed via, in sections, up thus far, the place the rotary blades are caught, adopted by the lengthy auger.
About 20 metres of the auger within the chute has been minimize out, Mr Dhami advised reporters. A plasma cutter is being airlifted from Hyderabad to sort out the remaining 25 metres.
As soon as that occurs, guide drilling would start, he mentioned.