BMC To Kickstart Work Of Connecting Andheri’s Gokhale Bridge & Barfiwala Flyover In the present day; Challenge To Full Earlier than Monsoon


Mumbai: BMC To Kickstart Work Of Connecting Andheri’s Gokhale Bridge & Barfiwala Flyover In the present day; Challenge To Full Earlier than Monsoon | File

Mumbai: Following the submission of the ultimate report by the Indian Institute of Expertise (IIT), the Brihanmumbai Municipal Company (BMC) is about to embark on the duty of connecting the Gopal Krishna Gokhale Bridge with the CD Barfiwala Flyover in Andheri, ranging from Sunday night.

With a funds of Rs 8 crore allotted for the alignment work, the BMC goals to finish the mission inside 90 days, focusing on the tip of June or the primary week of July for its conclusion, simply across the begin of the monsoon.

Scheduled to kick off at 4 pm at the moment, the graduation of the mission will witness the presence of specialists from IIT and Veermata Jijabai Technological Institute (VJTI), who offered their preliminary technical insights in a report submitted to the civic physique on March 19, stated a report within the Indian Specific. Notably, VJTI’s report indicated that the merging of the 2 flyovers may very well be achieved with out the necessity for demolition.

BMC To Begin Work With out Floating Tender

In an effort to expedite the merging course of whereas navigating the constraints imposed by the continued mannequin code of conduct for the Lok Sabha polls, the BMC plans to have interaction one of many 5 contractors advisable by VJTI by way of the present contractor concerned within the building of the Gokhale bridge. This strategic method goals to bypass the formal tendering course of.

Beforehand, VJTI and IIT Bombay had been tasked with evaluating the feasibility of merging the 2 buildings, which offered a top disparity of two.8 meters (6 ft). VJTI’s interim report proposed elevating 4 spans for the merger and recognized 5 specialised companies able to executing the duty.

Acknowledging the procedural challenges posed by the mannequin code of conduct, BMC officers recognised the necessity to have interaction a contractor with out issuing a proper tender. Civic chief Bhushan Gagrani directed the involvement of one of many advisable contractors by way of the present contractor chargeable for the Gokhale bridge’s building. Moreover, Gagrani endorsed the interim measure of merging the north-side arm of the Barfiwala flyover with the Gokhale bridge.

The prevailing contractors, Freyssinet Prestressed Concrete and SMS Infra, will receive quotations for the merger from the advisable companies. A call on the chosen contractor and finalized phrases is anticipated quickly. Concurrently, preparations are underway to move girders for the northern facet of the Gokhale bridge from Ambala to Mumbai, with meeting set to start promptly following the company choice.